Action / result

Designed and produced in 1999 by CitéCréation, this trompe-l’œil of 450 m², in a painting representing items of the architecture of Old Quebec and emphasised by the intensity of the seasons, renders homage to the famous people who have marked the city’s history, including Jacques Cartier, Samuel de Champlain, the Count of Frontenac, Alphonse Desjardins, Thaïs Lacoste-Frémont, etc. along with Félix Leclerc and young ice hockey players.
The presence of this monumental mural design has had a radical impact on the image of Québec by restoring life and interest to an old and dingy wall and it participates in spreading the word about this old part of Quebec.
According to the Quebec Tourist Office, 3 million visitors a year come to admire and be photographed in front of this gigantic monumental mural design, a work that adds to the city’s identity and now one of its symbols.

The actors of the project

  • Contracting owner: Commission of the National Capital of Quebec.
  • Project manager: CitéCréation.
  • Partenaires: Partners: SODEC (Société de développement des Entreprises culturelles du Québec), Laurentide paints.

Budget et Technique

Cost of the monumental mural design project:

  • Project coordination/ Design / Production of 430 m of artistic mural painting.
  • €240 K ex. tax*.

The property in figures:

  • Building located at the edge of the tourist district of the city of Quebec.
  • Timetable for carrying out the project: 9 months.

Technical characteristics of the painted facades:

  • Stone wall covered in cement coating.

*Excluding scaffolding, surface preparation, team facilities, site office with access to water.